I was under the impression that you had to escrow for HPML apps taken on or after April 1.

I just took a training that said, closed on or after April 1.


Any takers?

Return to Top
Lending Compliance
#1363279 - 03/24/10 07:22 PM Re: HPML app taken on or after or closed on or after Always In Training
Doug Hendrickson Offline
Power Poster
Doug Hendrickson
Joined: Oct 2009
Posts: 3,927
We were probably in that same training from Harland. It's my understanding that escrow only applies to HPML loans where the APPLICATION was taken on or after April 1st, the same as your understanding!
_________________________
I hear and I forget. I see and I remember. I do and I understand.--Confucius

Return to Top
#1363283 - 03/24/10 07:25 PM Re: HPML app taken on or after or closed on or after Doug Hendrickson
Always In Training Offline
Diamond Poster
Joined: Jul 2006
Posts: 1,115
Where the Green Grass Grows
She scared me to death! I'm gonna have to re-do all my GFEs for the last week or so.

David Dickinson's Guru question here, says apps taken on or after 4/1.
Last edited by Always In Training; 03/24/10 07:26 PM.
Return to Top
#1363313 - 03/24/10 07:50 PM Re: HPML app taken on or after or closed on or after Always In Training
elebra Offline
100 Club
Joined: Apr 2009
Posts: 108
We were in the same training. Where can we go to support our understanding of apps taken on or after April 1?

Return to Top
#1363314 - 03/24/10 07:50 PM Re: HPML app taken on or after or closed on or after Always In Training
raitchjay Offline
Power Poster
Joined: Oct 2009
Posts: 9,108
OK
Same training here. smile
_________________________
I'm fixin' to fix that.

Return to Top
#1363319 - 03/24/10 07:57 PM Re: HPML app taken on or after or closed on or after raitchjay
Always In Training Offline
Diamond Poster
Joined: Jul 2006
Posts: 1,115
Where the Green Grass Grows
I'm emailing the trainers for all the RESPA training I've taken that the bank has paid for in the last year. I've printed David's guru question from here. I'm "building my case".

Return to Top
#1363324 - 03/24/10 08:04 PM Re: HPML app taken on or after or closed on or after Always In Training
Dan Persfull Offline
10K Club
Dan Persfull
Joined: Aug 2002
Posts: 47,532
Bloomington, IN
It's in 226.1's Commentary.

_________________________
The opinions expressed are mine and they are not to be taken as legal advice.

Return to Top
#1363333 - 03/24/10 08:09 PM Re: HPML app taken on or after or closed on or after Dan Persfull
Always In Training Offline
Diamond Poster
Joined: Jul 2006
Posts: 1,115
Where the Green Grass Grows
Let me just copy & paste that here as it's a little hard to find...


1. Effective dates . The Board’s revisions published on July 30, 2008 (the “final rules”) apply to covered loans (including refinance loans and assumptions considered new transactions under § 226.20) for which the creditor receives an application on or after October 1, 2009, except for the final rules on advertising, escrows, and loan servicing. But see comment 1(d)(3)-1. The final rules on escrow in § 226.35(b)(3) are effective for covered loans (including refinancings and assumptions in § 226.20) for which the creditor receives an application on or after April 1, 2010; but for such loans secured by manufactured housing on or after October 1, 2010.

Return to Top
#1363386 - 03/24/10 08:35 PM Re: HPML app taken on or after or closed on or after Always In Training
elebra Offline
100 Club
Joined: Apr 2009
Posts: 108
Thank you for that...it's always nice to see it in writing!

Return to Top

Moderator:  Andy_Z